Mumbai Metro Line 3 stations waterlogged amid heavy rains, services ‘temporarily curtailed’ on THESE routes | Watch

Mumbai Rains: Visuals on the internet showed rainwater flooding the underground metro stations in Mumbai as passengers waded through the water as they climbed up stairs and navigated through the stations.

Swastika Das Sharma
Published26 May 2025, 02:36 PM IST
Screengrab: Waterlogging at Worli Metro Station
Screengrab: Waterlogging at Worli Metro Station

Mumbai Rains: Heavy rainfall lashed Mumbai on Monday, May 26, as monsoon arrived in the city, causing severe waterlogging and flooding at underground metro stations.

Visuals on the internet showed rainwater flooding the underground metro stations in Mumbai as passengers waded through the water as they climbed up stairs and navigated through the stations.

The videos showed waterlogging issues inside the station premises, including platforms, ticketing bay and surrounding areas.

Watch the video of flooded Mumbai Metro station:

Mumbai Metro services curtailed

Metro services on some routes were temporarily halted, the Mumbai Metro Rail Corporation said in a post on X Monday.

Services on Metro Line 3 were curtailed, the metro operator said citing ‘technical issues’, with trains operating only up to Worli Station instead of Acharya Atre Chowk.

“Due to an unforeseen technical issue, train services on Metro Line-3 are temporarily curtailed and will operate only up to Worli Station instead of Acharya Atre Chowk . We sincerely regret the inconvenience caused,” it said.

Also Read | IMD ‘red’ alert for heavy rainfall in Mumbai, Thane until May 30
Also Read | Mumbai weather: Local trains delayed, traffic & flights impacted; check details

The MMRC, in a statement, said, “Due to the sudden and intense rainfall today, water seepage was reported at the under-construction entry/exit structure of Acharya Atrey Chowk station along Dr Annie Besant Road. The incident occurred when the RCC water-retaining wall constructed at entry/ exit collapsed due to a sudden ingress of water from an adjoining utility.”

As a precautionary measure and to ensure passenger safety, train services between Worli and Acharya Atrey Chowk have been temporarily suspended, the agency said.

However, the services from Aarey JVLR to Worli are not affected and are running regularly, it stated.

Waterlogging raises questions

The inundation inside the metro station has raised concerns about construction quality and monsoon preparedness of the underground metro station on the 33-km long Colaba-BKC-Aarey JVLR underground metro corridor.

Also Read | Mumbai weather LIVE: Trains, flights impacted as monsoon triggers heavy rains

On May 9, the MMRC extended the underground metro services between the Bandra-Kurla Complex and Aacharya Atre Chowk stations.

Metro Line 3 is Mumbai's first fully underground Metro line and is currently under phased construction.

Chief Minister Eknath Shinde visited the Disaster Management department amid 'Red' alert for heavy rains issued for Mumbai.

“Our aim is- no casualties. We are on alert mode,” he said.

“All agencies, including BMC, Army, and Navy, are on alert to work in coordination. The CM and the Disaster Management Minister are reviewing the situation. It is the government's duty to ensure that everything operates smoothly,” Shinde added.

Stay updated with the latest Trending, India , World and United States news. Follow all the latest updates on Israel Iran Conflict here on Livemint.

Business NewsNewsIndiaMumbai Metro Line 3 stations waterlogged amid heavy rains, services ‘temporarily curtailed’ on THESE routes | Watch
MoreLess